Technical supervision at the site: «Construction of Dzhubga-Sochi highway at the bypass of Sochi city.»
Customer
Limited Liability Company "Smolensk-DorNII-Proekt."
Time 01.02.2008 30.10.2009
Technical supervision and quality control at the facility: "Construction of Dzhubga-Sochi highway at the bypass of Sochi city, PK 134 - PK 194 in Krasnodar region"
The object characteristics:
- The overpass on PK98-PK102 is designed according to the layout 51+4х63+51 m frame construction
- The layout in the cross-section G- 15,4+2х1,5 m
- Side supports are monolithic, reinforced concrete, rack-mounted, bulkheads with foundations on drill pillars d = 1,5 m (individual design)
- Intermediate supports monolithic, reinforced concrete, rack-mount, thin-walled construction of individual design with foundations on drill pillars d = 1,5 m
- The span structure is steel-reinforced, threaded, with box-section beams and a monolithic reinforced concrete plate of the carriageway (individual design)