Final slide on bridge over Pur completed

On June 5, 2020, the final slide on the bridge over the Pur River was completed. Such a complex technological process took less than a day. Before the last stage of the launch, the engineers of the acceptance control service of Bridge Bureau LLC checked the readiness of all mechanisms and structures and gave permission to carry out the work. The slide of a structure weighing four and a half thousand tons was carried out under constant monitoring by our engineers. As a result, the path of 105 meters was covered in less than a day. Shore spans 1-2 and 10-11 will be mounted in a semi-mounted manner. Construction participants promise, that the first transport will pass over the bridge over the Pur River by the end of the year.